CONSTRUCTION UPDATES
mARCH 2024 Construction UPDATE:
35MW/65MW SOLAR ARRAY:
- Internal road construction is complete.
- Racking and Pile installation is complete.
- All electrical cables have been installed.
- Module deliveries complete.
- Fencing installation complete.
- Site stabilization and seeding work is ongoing.
- Vegetative screening work substantially completed..
- Majority of the project is in regular operation.
SUBSTATION
- Substation and Shared Facilities are complete.
Progress Photo:
August CONSTRUCTION UPDATE:
35MW Solar Array
- Internal road construction is complete
- Racking and Pile installation is complete.
- All electrical cables have been installed.
- Module deliveries for 24MW complete, 11MW expected in September 2022.
- 21MW is in regular operation
- Fencing installation is complete.
- Site stabilization and seeding work is ongoing.
- Vegetative screening work to begin in September 2022
65MW Solar Array
- Internal road construction complete
- Racking and Pile installation is complete.
- All electrical cables have been installed.
- Module instillation anticipated to begin in October 2022.
- Fencing installation is complete.
- Site stabilization and seeding work is ongoing.
- Vegetative screening work to begin in October 2022
SubStation
- Substation and Shared Facilities are complete